Friday, September 9, 2011

Weekly update 9/9

Top Completed and In-Process Items
State
Status
Upcoming Date/s
1
Work Space Imaging
·         We received approximately 50% of the sample PC needed in order to begin workstation image building.
·         This task is being moved out to week of 9/13 since all the equipment has arrived.  This task had been moved up in order to keep project moving while awaiting the equipment. 
·         Completed imaging the following; HP Mini 5102 and HP 6710b and all desktops completed (5700, 530 and 5100) with images applied along with drives.
In Process
green






2
Phase IV Kickoff
·         Reviewed the NEW Juniper firewall
Completed
Green



3
Cabled up all CAT6 at the CO location and documented
Completed
Green

4
Determined 10G interfaces with Kent.  Two ports will be secured by 9/15 off the blade center platform
In Progress
Green

5
Building out of the six VM Hosts
In Progress
Green

6
Configuration of Cisco switches
In Progress
Green



Current Punch list and Needs list
Date Requested
Date needed/complete
Resource
Status
1
McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed. Two 20m runs will be completed on 9/13/2011.
8/19/2011
9/13/2011
NKC Cablers
Yellow


2
McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date.  – Update- PC imaging has started, 3 pc’s have base installation of Windows XP software installed.  We have the following PC’s ready for imaging: laptops: HP Mini 5103, 2133, 2140  
8/19/2011
9/13/2011
NKC IT Personal
Green







Upcoming Activities
Start Date - Orig
State Date - Revised
Resource
Status
1
Initial configuration of SAN
8/29/2011

McGladrey
Green
4
Patching of software on the desktops (5700, 530, 5100)
9/13/2011

McGladrey
Green