Current Punch list and Needs list | Date Requested | Date needed/complete | Resource | Status | |
1 | Electricity has been delivered to the CO Datacenter. The other two sites will be completed next week. | 8/19/2011 | 9/2/2011 | NKC Electricians | Green |
2 | McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed. | 8/19/2011 | 9/2/2011 | NKC Cablers | Yellow |
3 | McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date. | 8/19/2011 | 9/13/2011 | NKC IT Personal | Green |
Upcoming Activities | Start Date - Orig | State Date - Revised | Resource | Status | |
1 | Initial configuration of SAN | 8/29/2011 | McGladrey | Green | |
2 | Build out of the six VM Hosts | 8/29/2011 | McGladrey | Green | |
3 | Configuration of Cisco Switches | 8/29/2011 | McGladrey | Green |