Friday, September 9, 2011

Weekly update 9/9

Top Completed and In-Process Items
State
Status
Upcoming Date/s
1
Work Space Imaging
·         We received approximately 50% of the sample PC needed in order to begin workstation image building.
·         This task is being moved out to week of 9/13 since all the equipment has arrived.  This task had been moved up in order to keep project moving while awaiting the equipment. 
·         Completed imaging the following; HP Mini 5102 and HP 6710b and all desktops completed (5700, 530 and 5100) with images applied along with drives.
In Process
green






2
Phase IV Kickoff
·         Reviewed the NEW Juniper firewall
Completed
Green



3
Cabled up all CAT6 at the CO location and documented
Completed
Green

4
Determined 10G interfaces with Kent.  Two ports will be secured by 9/15 off the blade center platform
In Progress
Green

5
Building out of the six VM Hosts
In Progress
Green

6
Configuration of Cisco switches
In Progress
Green



Current Punch list and Needs list
Date Requested
Date needed/complete
Resource
Status
1
McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed. Two 20m runs will be completed on 9/13/2011.
8/19/2011
9/13/2011
NKC Cablers
Yellow


2
McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date.  – Update- PC imaging has started, 3 pc’s have base installation of Windows XP software installed.  We have the following PC’s ready for imaging: laptops: HP Mini 5103, 2133, 2140  
8/19/2011
9/13/2011
NKC IT Personal
Green







Upcoming Activities
Start Date - Orig
State Date - Revised
Resource
Status
1
Initial configuration of SAN
8/29/2011

McGladrey
Green
4
Patching of software on the desktops (5700, 530, 5100)
9/13/2011

McGladrey
Green


Friday, September 2, 2011

The Project had a delayed start due to waiting for hardware and software to arrive. Rather than sit idle, the project team has moved up several of the latter phased tasks outlined in phase’s two and four of the overall project playbook. Since the kickoff of phase one has been delayed we are buying ourselves time from October tasks, which we should be able to use later to get the overall project back on time.

Activities underway or completed are;
·         The ‘needs’ list has been completed and delivered to the district for work space and access requirements.
·         Work station image creation and installation of Windows and applications.
·         Majority of the hardware and software has arrived and has been inventoried.  Specifically, the Cisco Gear has arrived, as well as the Avamar Gear, VMware and Microsoft Licenses and a few EMC SAN Hard Drive shelves.  Critical items still remaining are the HP Servers and EMC SAN Head Units.
·         Work space has been procured and we are in process of cleaning out the space needed in the server room to install a rack for the new equipment.  McGladrey will be working with the district electricians in order to run temporary power to the work area as well as district cable makers for some Fiber Runs.
·         Moved up phase IV of the project, which includes reconfiguration of the F5 load balancers and installation of the Juniper Firewalls.

McGladrey is working with the School District on a few specific needs;
·         Access to in house District Electricians to assist with electrical runs
·         Access to in house District LAN Cablers to create some Fiber Cable runs
·         Obtain like machines for each type of PC in production in order to build the base image for deployment on the Microsoft Network

Status update 9/2


Top Completed and In-Process Items
State
Status
Upcoming Date/s
1
Received all ordered Hardware and Software
Completed
Green

2
Perform Initial Rack/Stack of Equipment
·         Completed Winnetonka this week.
completed
Green



3
Work Space Imaging
·         We received approximately 50% of the sample PC needed in order to begin workstation image building.
·         This task is being moved out to week of 9/13 since all the equipment has arrived.  This task had been moved up in order to keep project moving while awaiting the equipment. 
In Process/Delayed
green




4
Phase IV Kickoff
·         We worked on reconfiguration of the F5 load balancers and installation of the Juniper Firewalls
In Process
Green



5.
Power has been pulled at the 3 nodes by Maintenance. 

completed
green



Current Punch list and Needs list
Date Requested
Date needed/complete
Resource
Status
1
Electricity has been delivered to the CO Datacenter.  The other two sites will be completed next week.
8/19/2011
9/2/2011

NKC Electricians
Green

2
McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed.
8/19/2011
9/2/2011
NKC Cablers
Yellow


3
McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date.  – Update- PC imaging has started, 3 pc’s have base installation of Windows XP software installed.  We have the following PC’s ready for imaging: laptops: HP Mini 5102, 5103, 2133, 2140 & HP 6710b - Desktops: HP dc5700sff, d530sff & D5200sff

8/19/2011
9/13/2011
NKC IT Personal
Green


Monday, August 29, 2011

Top Completed and In-Process Items
State
Status
Upcoming Date/s
1
Received all ordered Hardware and Software
Completed
Green

2
Perform Initial Rack/Stack of Equipment
·         All completed except Winnetonka, as the older rack had some active servers on it which cannot be powered down during normal business hours.  This will be completed on Monday.
In Process
Green



3
Work Space Imaging
·         We received approximately 50% of the sample PC needed in order to begin workstation image building.
·         This task is being moved out to week of 9/13 since all the equipment has arrived.  This task had been moved up in order to keep project moving while awaiting the equipment. 
In Process/Delayed
green




4
Phase IV Kickoff
·         We worked on reconfiguration of the F5 load balancers and installation of the Juniper Firewalls
In Process
Green





Current Punch list and Needs list
Date Requested
Date needed/complete
Resource
Status
1
Electricity has been delivered to the CO Datacenter.  The other two sites will be completed next week.
8/19/2011
9/2/2011

NKC Electricians
Green

2
McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed.
8/19/2011
9/2/2011
NKC Cablers
Yellow


3
McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date.
8/19/2011
9/13/2011
NKC IT Personal
Green




Upcoming Activities
Start Date - Orig
State Date - Revised
Resource
Status
1
Initial configuration of SAN
8/29/2011

McGladrey
Green
2
Build out of the six VM Hosts
8/29/2011

McGladrey
Green
3
Configuration of Cisco Switches
8/29/2011

McGladrey
Green