Top Completed and In-Process Items | State | Status | Upcoming Date/s | |
1 | Work Space Imaging · We received approximately 50% of the sample PC needed in order to begin workstation image building. · This task is being moved out to week of 9/13 since all the equipment has arrived. This task had been moved up in order to keep project moving while awaiting the equipment. · Completed imaging the following; HP Mini 5102 and HP 6710b and all desktops completed (5700, 530 and 5100) with images applied along with drives. | In Process | green | |
2 | Phase IV Kickoff · Reviewed the NEW Juniper firewall | Completed | Green | |
3 | Cabled up all CAT6 at the CO location and documented | Completed | Green | |
4 | Determined 10G interfaces with Kent. Two ports will be secured by 9/15 off the blade center platform | In Progress | Green | |
5 | Building out of the six VM Hosts | In Progress | Green | |
6 | Configuration of Cisco switches | In Progress | Green |
Current Punch list and Needs list | Date Requested | Date needed/complete | Resource | Status | |
1 | McGladrey will need access to in house District LAN Cablers to create some Fiber Cable runs from the front of the CO Datacenter to the rear where the temp rack will be installed. Two 20m runs will be completed on 9/13/2011. | 8/19/2011 | 9/13/2011 | NKC Cablers | Yellow |
2 | McGladrey will need to obtain for each PC in production a like machine that can be used to build the base image for deployment on the Microsoft Network - obtained 50% of them to date. – Update- PC imaging has started, 3 pc’s have base installation of Windows XP software installed. We have the following PC’s ready for imaging: laptops: HP Mini 5103, 2133, 2140 | 8/19/2011 | 9/13/2011 | NKC IT Personal | Green |
Upcoming Activities | Start Date - Orig | State Date - Revised | Resource | Status | |
1 | Initial configuration of SAN | 8/29/2011 | McGladrey | Green | |
4 | Patching of software on the desktops (5700, 530, 5100) | 9/13/2011 | McGladrey | Green |